Sunday, February 19, 2012

Going on 5 weeks in boatyard

Damn I am getting sick of the excuses from the Phasor Generator installer.  He forgot to hook up the exhaust and bilge pump hoses and placed the generator pan over them.  Soooo we have to remove all that work and replace the hoses b4 any more work can be done.

Additionally, we lost 5 days so he could attend the Miami Boat Show.  I am losing faith in his installation.

Sunday, January 29, 2012

The latest on Genesis.

Generator install moving along expect to have it finished by end of week.  This week was kinda slow with the fuel tank removal and install of the sound sheilding taking.
 
Talked to the yard guy who does the hull compounding and waxing so he is on it.

Wednesday, January 25, 2012

On The Hard

Bottom job, generator install

Sunday, January 8, 2012

Winter Haulout

Getting ready for a bottom job at our favorite repair facility Salt Creek Marina.  Genoa needs some stiching and of course the generator install.  Thinking middle of January.